1. Pick a depth
For a new driveway, plan a compacted base of crusher run (ABC) around 4–6 inches, often with a top layer of #57 or washed stone. Soft or wet ground, or heavy trucks, call for more. Refreshing an existing gravel driveway usually takes about 2 inches on top.
2. Calculate cubic yards
Length (ft) × Width (ft) × Depth (in) ÷ 12 ÷ 27 = cubic yards
Dividing by 12 turns inches into feet; dividing by 27 turns cubic feet into cubic yards.
3. Convert to tons
Crushed stone weighs roughly 1.4 tons per cubic yard (it varies with the stone and moisture). Multiply cubic yards by 1.4 to estimate tons. Our trucks carry about 20 tons per load.
Worked examples
| DRIVEWAY | DEPTH | CUBIC YARDS | TONS (≈) | TRUCKLOADS |
|---|---|---|---|---|
| 60 ft × 12 ft | 4 in | 8.9 | 12.4 | 1 |
| 100 ft × 12 ft | 4 in | 14.8 | 20.7 | 1–2 |
| 100 ft × 12 ft | 6 in | 22.2 | 31.1 | 2 |
| 200 ft × 14 ft | 6 in | 51.9 | 72.6 | 4 |
Skip the math: enter your numbers in our material calculator, then send the result straight to a quote. Dispatch confirms the exact amount before delivery.
Which stone?
Crusher run packs into a hard base; #57 drains and gives a clean top. See #57 stone vs crusher run for the full comparison.